Project Description:
PITTSFIELD- SOUTH STREET (ROUTE 7) STREETSCAPE ENHANCEMENT (PHASE I)
This project has two locations: a 1400-foot portion of South Street from Housatonic Street north to the intersection of West and East Streets and a 470-foot portion of Union Street from Center Street east to North Street. Pavement markings and signage will be upgraded. Most existing crosswalks within the project limits will be built with paver surfaces. Sidewalks at both locations will be reconstructed with cement concrete and accent pavers in various locations edged by granite curbing and will be Americans with Disabilities Act compliant. East-bound on Union Street the curb will be moved to allow for a widened cross section with 11-foot wide eastbound and westbound travel lanes and an 8-foot parking lane on the eastbound side of Union Street. The 6.5-foot grass strip on the westbound travel lane of Union Street will be retained.
Location:
  • City of Pittsfield
  • Resident Engineer: Timothy Moore
    Construction Contract Value: $1,376,476.69
    Construction Bid Price: $1,134,279.00
    Initial Construction Estimate: $1,147,507.50
    District: District 1

    Contracts (1) Progress
    # 57206 -- Construction Contract
    Pittsfield - Roadway Reconstruction and Related Work on a Section of Route 7 (South Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/23/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/14/2006
    Project Status Advertised 07/26/2008
    Project Management
    100% Design 100% Package Received 01/02/2008
    100% Design 100% Package Received 05/09/2008
    100% Design 100% Package Comments to DE 02/29/2008
    100% Design 100% Package Comments to DE 06/23/2008
    25% Design 25% Package Received 12/05/2006
    25% Design 25% Package Comments to DE 03/22/2007
    25% Design Design Public Hearing 05/17/2007
    75% Design 75% Package Received 07/03/2007
    75% Design 75% Package Comments to DE 12/03/2007
    Final Design PS&E Received 07/03/2008
    Final Design PS&E to FAPRO 07/22/2008