Project Description:
NORTHAMPTON- IMPROVEMENTS ON I-91 INTERCHANGE 19 AT ROUTE 9 AND DAMON ROAD
This project will consist of the construction of a two-lane roundabout at the intersection of Route 9 and Damon Road/I-91 NB off ramp, and signal upgrades and improvements at the I-91 SB on ramp. Other improvements will include increased bicycle accommodations and access, along with 5 ft. sidewalks and crossings for improved pedestrian use.
Location:
  • City of Northampton
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Nicholas Corey
    Construction Bid Price: $7,075,910.40
    District: District 2

    Contracts (3) Progress
    # 105762 -- Construction Contract
    Roundabout Construction and Related Work (Including Signals) Interstate 91, Interchange 19 at Route 9 (Bridge Street) and Damon Road Completed
    # 53495 -- Design -- Highway
    Work will consist of providing preliminary, final engineering design and construction phase services for design of I-91 Interchange #19/Route 9/Damon Road in Northampton. Final
    # 86005 -- Design -- Services
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/01/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 08/29/2005
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 01/16/2018
    100% Design 100% Package Comments to DE 02/05/2018
    25% Design 25% Package Received 04/27/2015
    25% Design 25% Package Comments to DE 06/02/2015
    25% Design 25% Package Approved 04/27/2016
    25% Design Design Public Hearing 06/02/2016
    25% Design 25% Plans Complete 04/27/2016
    75% Design 75% Package Received 03/03/2017
    75% Design 75% Package Comments to DE 05/05/2017
    75% Design 75% Plans Approved 05/05/2017
    Final Design PS&E Received 06/04/2018
    Final Design PS&E Received - Resub 1 07/31/2018
    Consultant Contract Process Scope to DE 01/02/2008
    Consultant Contract Process NTP Issued 04/30/2009
    Consultant Contract Process Workhours Approved 10/17/2008