| Project Description: |
CHICOPEE- SPRINGFIELD- INTERSTATE MAINTENANCE & RELATED WORK ON I-91
The work consists of the resurfacing of I-91 from the north end of the viaduct at the junction of I-291 to the Connecticut River Bridge in Chicopee at the Junction of I-391. The project also includes bridge preservation work such as deck repairs, joint replacements, and bridge railing retrofits subject to the availability of funds.
|
| Location: |
|
| Resident Engineer: | George Pelletier![]() |
| Construction Contract Value: | $19,978,437.00 |
| Construction Bid Price: | $17,208,243.25 |
| Initial Construction Estimate: | $15,759,106.40 |
| District: | District 2 |
|