Project Description:
CHICOPEE- SPRINGFIELD- INTERSTATE MAINTENANCE & RELATED WORK ON I-91
The work consists of the resurfacing of I-91 from the north end of the viaduct at the junction of I-291 to the Connecticut River Bridge in Chicopee at the Junction of I-391. The project also includes bridge preservation work such as deck repairs, joint replacements, and bridge railing retrofits subject to the availability of funds.
Location:
  • City of Chicopee
  • City of Springfield
  • Resident Engineer: George Pelletier
    Construction Contract Value: $19,978,437.00
    Construction Bid Price: $17,208,243.25
    Initial Construction Estimate: $15,759,106.40
    District: District 2

    Contracts (1) Progress
    # 57890 -- Construction Contract
    Resurfacing, Bridge and Related work on a Section of Interstate I-91. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/17/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 11/28/2005
    Project Status Advertised 11/22/2008
    Project Management
    Final Design PS&E Received 09/12/2008
    Final Design PS&E to FAPRO 10/20/2008
    Consultant Contract Process NTP Issued 01/01/2008