| Project Description: |
CHICOPEE- SPRINGFIELD- INTERSTATE MAINTENANCE & RELATED WORK ON I-91
The work consists of the resurfacing of I-91 from the north end of the viaduct at the junction of I-291 to the Connecticut River Bridge in Chicopee at the Junction of I-391. The project also includes bridge preservation work such as deck repairs, joint replacements, and bridge railing retrofits subject to the availability of funds.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Albert Li![]() |
| Estimated Total Contract Cost: | $19,978,437.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 2 |
| Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
||||||
|
|
|
||