Project Description: |
ACTON- CONCORD- LITTLETON- HARVARD- TRAFFIC SIGN REPLACEMENT & SAFETY IMPROVEMENTS ON ROUTE 2
This project will replace and update all overehad and ground mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on the Route 2 mainline and intersecting secondary roadways from the Route 110/111 interchange (Exit 38) in Harvard easterly to the Route 2A intersection (Concord Rotary) in Concord.
|
Location: |
|
Resident Engineer: | Steven Miller |
Construction Contract Value: | $2,136,901.80 |
Construction Bid Price: | $2,026,021.80 |
Initial Construction Estimate: | $2,846,667.00 |
District: | District 3 |
|
Bridges |
|
|
|
|