Project Description: |
FITCHBURG- BRIDGE REPLACEMENT, F-04-053, ASHBY WEST ROAD OVER THE SCOTT RESERVOIR OUTLET
The Ashby West Road bridge over the Scott Reservoir Outlet is a structurally deficient, functionally obsolete structure. The purpose of this project is to replace the bridge with a single span superstructure. The proposed abutments are to be located behind the existing abutments. A detour will be established during construction.
|
Location: |
|
Resident Engineer: | Stephen Romano |
Construction Contract Value: | $1,034,552.00 |
Construction Bid Price: | $890,480.00 |
Initial Construction Estimate: | $1,021,212.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|