FITCHBURG- BRIDGE REPLACEMENT, F-04-053, ASHBY WEST ROAD OVER THE SCOTT RESERVOIR OUTLET
The Ashby West Road bridge over the Scott Reservoir Outlet is a structurally deficient, functionally obsolete structure. The purpose of this project is to replace the bridge with a single span superstructure. The proposed abutments are to be located behind the existing abutments. A detour will be established during construction.
Location:
  • City of Fitchburg
  • Resident Engineer: Stephen Romano
    Construction Contract Value: $1,034,552.00
    Construction Bid Price: $890,480.00
    Initial Construction Estimate: $1,021,212.00
    District: District 3

    Contracts (2) Progress
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 66091 -- Construction Contract
    Bridge Replacement (F-04-053) (Concrete Carbon Fiber Pipe) – Ashby West Road over the Scott Reservoir Outlet. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/18/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 09/21/2005
    Project Status Advertised 06/19/2010
    Project Management
    25% Design 25% Package Received 12/02/2009
    25% Design 25% Package Comments to DE 02/23/2010
    25% Design Design Public Hearing 12/09/2009
    75% Design 75% Package Received 05/04/2010
    75% Design 75% Package Comments to DE 05/21/2010
    Final Design PS&E Received 05/28/2010
    Final Design PS&E Received 06/15/2010
    Final Design PS&E to FAPRO 06/15/2010
    Consultant Contract Process Scope to DE 08/11/2009
    Consultant Contract Process NTP Issued 11/06/2009