Project Description:
BERKLEY- BRIDGE REPLACEMENT, B-08-003, PADELFORD STREET OVER STATE ROUTE 24 (DESIGN-BUILD)
The purpose of this project is the replace the bridge carrying Padelford Street Bridge over Route 24. The project also involves roadway improvements on both approaches, and necessary improvement on-ramps.
Location:
  • Town of Berkley
  • Resident Engineer: Alfredo Nunez
    Construction Contract Value: $6,391,406.00
    Construction Bid Price: $5,657,460.00
    Initial Construction Estimate: $5,342,510.00
    District: District 5

    Contracts (4) Progress
    # 37072 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 57729 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 60537 -- Construction Contract
    Hollis E. Jennings Bridge Replacement (B-08-003) (Steel) - Padelford Street over Route 24. DESIGN/BUILD. Completed
    # 69755 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/31/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/27/2005
    Project Status Initiated 10/04/2005
    Project Status Advertised 06/01/2013
    Project Management
    25% Design 25% Package Received 05/12/2011
    25% Design 25% Package Received 10/11/2011
    25% Design 25% Package Received 08/07/2012
    25% Design 25% Package Received 05/23/2013
    25% Design 25% Package Comments to DE 04/09/2012
    25% Design 25% Package Comments to DE 04/09/2012
    25% Design 25% Package Comments to DE 09/18/2012
    25% Design 25% Package Comments to DE 01/18/2013
    25% Design 25% Package Approved 01/08/2013
    25% Design Design Public Hearing 03/26/2012
    25% Design 25% Plans Complete 12/07/2012
    Final Design PS&E Received 05/23/2013
    Final Design PS&E to FAPRO 05/30/2013
    Consultant Contract Process Scope to DE 10/14/2005
    Consultant Contract Process NTP Issued 10/10/2008