Project Description: |
BERKLEY- BRIDGE REPLACEMENT, B-08-003, PADELFORD STREET OVER STATE ROUTE 24 (DESIGN-BUILD)
The purpose of this project is the replace the bridge carrying Padelford Street Bridge over Route 24. The project also involves roadway improvements on both approaches, and necessary improvement on-ramps.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Jason L Benoit![]() |
Estimated Total Contract Cost: | $6,391,406.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|