Project Description:
|
DISTRICT 4- SCHEDULED & EMERGENCY DRAWBRIDGE REPAIRS AND OPERATIONS (NORTH AREA - CONTRACT 2)
|
Location:
|
Town of Amesbury
Town of Groveland
City of Haverhill
Town of Newbury
City of Newburyport
Town of Salisbury
|
Resident Engineer:
|
William Bernard |
Construction Contract Value:
|
$2,813,710.00 |
Construction Bid Price:
|
$2,063,710.00 |
Initial Construction Estimate:
|
$2,247,365.00 |
District:
|
District 4 |
Current Status:
|
The completion date for this contract was 6/21/2008 (as of 07/30/2008) |
Additional Info:
|
The Newburyport/Salisbury Drawbridge is manned 6 AM to 10 PM, May 1 through November 15; Otherwise 1 hr advance notice is needed.
Futhermore, Memorial day to Labor Day, the bridge opens only on the hour and the half hour.
The Plum Island Drawbridge requires 1 hour advance notice April 1 through November 30, 5 AM TO 9 PM; otherwise 3 hours advance notice is needed. The Essex Merrimack, Rocks Village and Haverhill/Groveland Drawbridges require 2 hour advance notice for openings. (as of 07/30/2008) |