Project Description:
WOBURN- INTERSTATE RESURFACING ON I-95
Location:
  • City of Woburn
  • Resident Engineer: Brian Noel
    Construction Contract Value: $11,631,077.00
    Construction Bid Price: $9,840,411.39
    Initial Construction Estimate: $9,089,396.00
    District: District 4

    Contracts (1) Progress
    # 54542 -- Construction Contract
    The work shall consist of full width asphalt paving excavation by cold planer and overlaying with hot mixed asphalt (HMA) on I-95 in Woburn. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/13/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/01/2005
    Project Status Initiated 10/17/2005
    Project Status Advertised 09/08/2007
    Project Management
    Final Design PS&E Received 09/05/2007
    Final Design PS&E to FAPRO 09/06/2007