Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LYNN- INTERSECTION IMPROVEMENTS AT LYNNFIELD STREET (ROUTE 129) MILLARD AVENUE, PARKER HILL AVENUE, DEN QUARRY ROAD
The proposed project consists of roadway resurfacing, new curb with cement concrete sidewalks, wheelchair ramps, geometric improvements at intersections, new signing and pavement markings, new signalized intersection to improve safety and efficiency, drainage improvements, a culvert extension, pavement markings, and incidental work. The project length is 847 feet (0.16 miles).
Location:
  • City of Lynn
  • Resident Engineer: Michael McGeoch
    Construction Contract Value: $688,367.00
    Construction Bid Price: $511,243.07
    Initial Construction Estimate: $830,669.00
    District: District 4

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 65712 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) Lynnfield Street (Route 129) at Millard and Parker Hill Avenues and Dan Quarry Road. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/17/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/09/2005
    Project Status Initiated 10/17/2005
    Project Status Advertised 07/10/2010
    Project Management
    100% Design 100% Package Received 11/09/2009
    100% Design 100% Package Comments to DE 02/12/2010
    25% Design 25% Package Received 04/12/2007
    25% Design Design Public Hearing 10/30/2007
    75% Design 75% Package Received 04/07/2008
    75% Design 75% Package Comments to DE 06/25/2009
    Final Design PS&E Received 04/26/2010
    Final Design PS&E to FAPRO 07/07/2010