Project Description:
MARSHFIELD- BRIDGE REPLACEMENT, M-07-007, BEACH STREET OVER THE CUT RIVER
The purpose of this project is to replace a locally owned, structurally deficient bridge carrying Beach Street over the Cut River in Marshfield in the same location with two sidewalks.
Location:
  • Town of Marshfield
  • Construction Begins: Summer 2018
    Resident Engineer: Peter Benkart
    Construction Bid Price: $3,375,660.57
    District: District 5

    Contracts (3) Progress
    # 102813 -- Construction Contract
    Bridge Replacement Br. No. M-07-007 (Precast Concrete Deck Beams) Beach Street over the Cut River. Completed
    # 34490 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 5 - Contract A Final
    # 69764 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/20/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 10/18/2005
    Project Status Advertised 11/25/2017
    Project Management
    100% Design 100% Package Received 05/22/2017
    25% Design 25% Package Received 02/25/2015
    25% Design 25% Package Received 10/19/2015
    25% Design 25% Package Comments to DE 07/17/2015
    25% Design 25% Package Comments to DE 02/29/2016
    25% Design Design Public Hearing 05/19/2016
    75% Design 75% Package Received 10/31/2016
    75% Design 75% Package Comments to DE 01/05/2017
    Final Design PS&E Received 10/16/2017
    Final Design PS&E to FAPRO 11/14/2017
    Consultant Contract Process Scope to DE 10/25/2005
    Consultant Contract Process NTP Issued 06/09/2006
    Consultant Contract Process Workhours Approved 12/03/2013