Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
EASTON- RECONSTRUCTION & IMPROVEMENTS AT ROUTE 106 AND ROUTE 123 (FIVE CORNERS)
The improvements associated with this project include the installation of a new fully actuated traffic signal system with appropriate phasing and timing for peak hour demands. Foundry Street will be widened to provide a second exclusive left-turn lane eastbound and one exclusive left-turn lane westbound. Bay Road, to the north of the intersection, will be relocated approximately 100 feet to the northeast to provide additional vehicle storage between the intersections and to provide a 90 degree intersection. Existing traffic signal systems, pavement markings and signs will also be upgraded to meet with the proposed design.
Location:
  • Town of Easton
  • Resident Engineer: John Bielski
    Construction Contract Value: $1,712,796.70
    Construction Bid Price: $1,489,021.00
    Initial Construction Estimate: $1,984,166.50
    District: District 5

    Contracts (1) Progress
    # 65278 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signal Improvements) at the Intersection of Route 106 and 123 (Five Corners). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/28/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 12/01/2005
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 11/29/2006
    Project Status Initiated 10/25/2005
    Project Status Advertised 06/05/2010
    Project Management
    100% Design 100% Package Received 04/12/2010
    25% Design 25% Package Received 04/09/2008
    25% Design 25% Package Comments to DE 11/25/2008
    25% Design Design Public Hearing 12/02/2008
    75% Design 75% Package Received 06/18/2009
    75% Design 75% Package Comments to DE 11/27/2009
    Final Design PS&E to FAPRO 06/02/2010