Project Description:
NORTHAMPTON- ADDITIONS AND RENOVATIONS TO ADMINISTRATION BUILDING
Work consists of additions and renovations at the MassDOT - Highway Division District 2 Administration building. Work includes adding office space above the existing warehouse, converting existing warehouse space into offices, creating a training facility/auditorium, constructing a new addition adjacent to the existing garage for supplies storage, and construction of 2 garage bays for BridgeMaster bridge inspection vehicles. The work also includes new parking spaces, construction of a new elevator, conversion of the existing auditorium into offices and various ADA compliant building upgrades. Related work includes the removal of existing walls, fences and windows, concrete cutting and demolition, patching existing masonry walls, construction of permanent metal frame walls, installation of new drop ceilings, installation of new vinyl tile, seamless epoxy flooring and carpeting, installation of movable partitions, installation of new heating and cooling system, installation of lighting, light switches and electrical outlets, installation of telephones, wiring, and jacks compatible with existing system, and installation of new audio and video conferencing and training equipment.
Location:
  • City of Northampton
  • Resident Engineer: Anthony Kuralowicz
    Construction Contract Value: $6,034,050.00
    Construction Bid Price: $5,247,000.00
    Initial Construction Estimate: $5,734,500.00
    District: District 2

    Contracts (2) Progress
    # 61531 -- Design -- Services
    Work will consist of repairs and renovations to existing buildings. Final
    # 74817 -- Construction Contract
    Addition and Renovations to the District 2 Administration Building. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/27/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 10/26/2005
    Project Status Advertised 08/04/2012
    Project Management
    100% Design 100% Package Received 06/14/2012
    100% Design 100% Package Comments to DE 06/18/2012
    25% Design 25% Package Received 01/10/2012
    25% Design 25% Package Comments to DE 01/20/2012
    25% Design 25% Package Approved 01/31/2012
    25% Design 25% Plans Complete 01/27/2012
    75% Design 75% Package Received 04/12/2012
    75% Design 75% Package Comments to DE 04/27/2012
    75% Design 75% Plans Approved 05/03/2012
    75% Design 75% Plans Complete 04/27/2012
    Final Design PS&E Received 07/31/2012
    Final Design PS&E to FAPRO 07/31/2012