QUINCY- CENTER CONCOURSE IMPROVEMENTS ON REVERE ROAD (MCGRATH HIGHWAY - PHASE II)
This 1900-foot project includes roadway and sidewalk reconstruction and new traffic signals along the new alignment from the end of the Highway Division's Phase I project to the project limit west of the Washington Street intersection. A 600 ft section of Quincy Avenue/Hancock Street is proposed for reconstruction including the intersection with Elm Street/School Street. The project continues along Elm Street improving the roadway layout and corner geometries. Construction advances onto Mechanic Street for 500 feet concluding at the intersection with Revere Road.
Location:
  • City of Quincy
  • Resident Engineer: Kevin Solimine
    Construction Contract Value: $5,208,883.00
    Construction Bid Price: $5,075,947.37
    Initial Construction Estimate: $7,543,847.30
    District: District 4

    Contracts (1) Progress
    # 62563 -- Construction Contract
    Roadway Reconstruction and Signal Improvements on Sections of Elm, Hancock, Mechanic & School Streets and Revere Road (Quincy Center Concourse) - Phase II) (ARRA) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/19/2005
    Project Status Initiated 10/26/2005
    Project Status Advertised 01/23/2010
    Project Management
    100% Design 100% Package Received 03/10/2009
    100% Design 100% Package Comments to DE 06/23/2009
    25% Design 25% Package Received 11/01/2006
    25% Design 25% Package Comments to DE 04/18/2007
    25% Design Design Public Hearing 05/30/2007
    75% Design 75% Package Received 05/27/2008
    75% Design 75% Package Comments to DE 02/05/2009
    Final Design PS&E Received 11/03/2009
    Final Design PS&E to FAPRO 01/14/2010