Project Description:
WEST STOCKBRIDGE- BRIDGE REPLACEMENT, W-22-004, ROUTE 41 (GREAT BARRINGTON ROAD) OVER WILLIAMS RIVER
The purpose of this project is to replace the existing structurally deficient bridge structure carrying Great Barrington Road over the Williams River with a new bridge structure. The existing structure, built in 1927 is a single-span concrete tee beam superstructure with a concrete deck and bituminous wearing surface. The bridge length is approximately 50 feet and the out-to-out deck width is 34.5 feet. Curb width is 30 feet. The demolition of the existing bridge and construction of the new proposed NEXT Beam superstructure bridge supported on spread footings will utilize Stage Construction.
Location:
  • Town of West Stockbridge
  • Resident Engineer: Anthony Vona
    Construction Contract Value: $2,567,887.00
    Construction Bid Price: $2,229,684.35
    Initial Construction Estimate: $1,955,274.94
    District: District 1

    Contracts (5) Progress
    # 31228 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 2 Final
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 83653 -- Construction Contract
    Bridge Replacement (W-22-004) (NEXT Beams) Route 41 (Great Barrington Road) over the Williams River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/08/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Status Initiated 11/03/2005
    Project Status Advertised 07/19/2014
    Project Management
    25% Design 25% Package Received 03/21/2012
    25% Design 25% Package Comments to DE 05/07/2012
    25% Design 25% Package Comments to DE 10/15/2013
    25% Design 25% Package Approved 06/14/2012
    25% Design Design Public Hearing 07/10/2012
    25% Design 25% Plans Complete 05/07/2012
    75% Design 75% Package Received 11/29/2012
    75% Design 75% Package Comments to DE 01/04/2013
    Final Design PS&E Received 11/04/2013
    Final Design PS&E Received 03/17/2014
    Final Design PS&E Received 05/23/2014
    Final Design PS&E Received 06/26/2014
    Final Design PS&E to FAPRO 07/17/2014
    Consultant Contract Process Scope to DE 04/26/2011
    Consultant Contract Process NTP Issued 08/23/2011
    Consultant Contract Process Workhours Approved 07/15/2011