Project Description: |
NEWBURYPORT- MULTI-USE TRAIL CONSTRUCTION (PHASE I) INCLUDES 2 BRIDGES
The Clipper City Rail Trail will extend from just south of Parker Street to the Merrimac River utilizing Executive Office of Transportation railroad right of way. One bridge will be incorporated in the project over Low Street. The trail will extend just over one mile in length.
|
Location: |
|
Resident Engineer: | Raymond Orsini |
Construction Contract Value: | $3,073,310.00 |
Construction Bid Price: | $2,736,064.00 |
Initial Construction Estimate: | $2,759,841.00 |
District: | District 4 |
|