Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
NEWBURYPORT- MULTI-USE TRAIL CONSTRUCTION (PHASE I) INCLUDES 2 BRIDGES
The Clipper City Rail Trail will extend from just south of Parker Street to the Merrimac River utilizing Executive Office of Transportation railroad right of way. One bridge will be incorporated in the project over Low Street. The trail will extend just over one mile in length.
Location:
  • City of Newburyport
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Albert Miller
    Estimated Total Contract Cost: $3,073,310.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project has been advertised for construction bids. (as of 09/22/2007 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/20/2005
    Project Status Initiated 11/21/2005
    Project Status Advertised 09/22/2007
    Project Management
    100% Design 100% Package Received 08/20/2007
    25% Design 25% Package Received 02/21/2007
    25% Design 25% Package Received 03/19/2007
    25% Design 25% Package Comments to DE 12/11/2006
    75% Design 75% Package Received 06/01/2007
    75% Design 75% Package Comments to DE 07/18/2007
    Final Design PS&E to FAPRO 09/18/2007