ARLINGTON- RECONSTRUCTION OF MASSACHUSETTS AVENUE, FROM POND LANE TO THE CAMBRIDGE C.L.
This proposed project will reconstruct Massachusetts Avenue in the Town of Arlington from Pond Lane to the Cambridge City Line. The work includes the reconstruction of existing pavements, lane reconfiguration, and traffic signal and access improvements. The construction will improve the vehicular, bicycle and pedestrian movement, enhance streetscape, and also improve safety within the project area by improving the roadway crossings and thereby creating a more orderly traffic flow.
Location:
  • Town of Arlington
  • Resident Engineer: John McGillicuddy
    Construction Contract Value: $6,728,287.00
    Construction Bid Price: $5,978,060.50
    Initial Construction Estimate: $5,355,115.50
    District: District 4

    Contracts (4) Progress
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79877 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) along a Section of Massachusetts Avenue (Routes 2A & 3). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/30/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/20/2005
    Project Status Initiated 11/21/2005
    Project Status Advertised 09/21/2013
    Project Management
    100% Design 100% Package Received 04/30/2013
    25% Design 25% Package Received 09/17/2009
    25% Design 25% Package Received 11/19/2010
    25% Design 25% Package Comments to DE 01/31/2011
    25% Design 25% Package Approved 07/13/2011
    25% Design Design Public Hearing 04/12/2011
    25% Design Design Public Hearing 02/26/2013
    75% Design 75% Package Received 02/29/2012
    75% Design 75% Package Comments to DE 08/24/2012
    Final Design PS&E Received 09/04/2013
    Final Design PS&E Received 10/07/2013
    Final Design PS&E to FAPRO 09/11/2013