Project Description:
WORCESTER- BRIDGE REHABILITATION, W-44-010, (STATE ROUTE 12) WEBSTER STREET OVER MIDDLE RIVER
The purpose of this project is to rehabilitate the existing bridge carrying Webster Street over Middle River due to its historical significance. If the rehabilitation is not reasonable due to extreme costs and/or safety, the bridge is to be replaced.
Location:
  • City of Worcester
  • Resident Engineer: Stephen Shamoian
    Construction Contract Value: $2,848,023.00
    Construction Bid Price: $2,489,147.00
    Initial Construction Estimate: $2,680,245.00
    District: District 3

    Contracts (6) Progress
    # 54821 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71230 -- Construction Contract
    Bridge Replacement (W-44-010) (Concrete) - Webster Street (Route 12) over the Middle River. (ABP) Completed
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/18/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/27/2005
    Project Status Initiated 11/25/2005
    Project Status Advertised 09/24/2011
    Project Management
    25% Design 25% Package Received 02/23/2010
    25% Design 25% Package Received 11/30/2010
    25% Design 25% Package Comments to DE 12/21/2010
    25% Design Design Public Hearing 03/16/2011
    25% Design 25% Plans Complete 12/21/2010
    75% Design 75% Package Received 05/13/2011
    Final Design PS&E Received 09/12/2011
    Final Design PS&E to FAPRO 09/21/2011
    Consultant Contract Process Scope to DE 02/11/2009
    Consultant Contract Process NTP Issued 03/26/2009