PITTSFIELD- SIGNAL & INTERSECTION IMPROVEMENTS AT ROUTE 7 (NORTH STREET) AND ROUTE 9 (PARK SQUARE)
The purpose of this project is to improve traffic and safety at the three intersections surrounding Park Square. These intersections currently experience unacceptable levels of peak period congestion and delay, a high number of traffic accidents, and long queues of stopped vehicles under existing peak demand conditions during weekday commuting periods. The Park Square area is also included in the city's streetscape project. As a part of this project, a variety of pavement and sidewalk treatments will be implemented at the Park Square location.
Location:
  • City of Pittsfield
  • Resident Engineer: Stephen Eddington
    Construction Contract Value: $1,987,786.98
    Construction Bid Price: $2,538,919.50
    Initial Construction Estimate: $2,427,056.25
    District: District 1

    Contracts (1) Progress
    # 57334 -- Construction Contract
    Pittsfield - Intersection Improvements Route 7 (South Street) & Route 9 (Park Square) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/13/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/06/2007
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/27/2005
    Project Status Initiated 11/25/2005
    Project Status Advertised 09/06/2008
    Project Management
    100% Design 100% Package Received 06/19/2008
    100% Design 100% Package Comments to DE 07/25/2008
    25% Design 25% Package Received 08/17/2007
    25% Design 25% Package Comments to DE 10/26/2007
    25% Design Design Public Hearing 10/18/2007
    75% Design 75% Package Received 12/21/2007
    75% Design 75% Package Comments to DE 03/10/2008
    Final Design PS&E Received 09/03/2008
    Final Design PS&E to FAPRO 09/03/2008