Project Description: |
LOWELL- CONNECTOR RECONSTRUCTION, FROM THORNDIKE STREET TO GORHAM STREET
This project would entail reconstruction of the intersection of the Lowell Connector at Route 3A (Gorham Street) and replacement of the existing traffic signals.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Spring 2028 |
Project Manager: | Kimberley Sloan |
Estimated Total Contract Cost: | $10,066,437.16 |
Estimated Total Federal Participating Construction Cost: | $10,811,351.42 |
Funding Provision: | This project is planned to be funded through the 2028 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | 25% Package Received (as of 05/24/2024 ) |
|
Bridges |
|
|
|