LOWELL- CONNECTOR RECONSTRUCTION, FROM THORNDIKE STREET TO GORHAM STREET
This project would entail reconstruction of the intersection of the Lowell Connector at Route 3A (Gorham Street) and replacement of the existing traffic signals.
Location:
  • City of Lowell
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2028
    Project Manager: Kimberley Sloan
    Estimated Total Contract Cost: $5,156,087.40
    Estimated Total Federal Participating Construction Cost: $6,287,510.30
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Northern Middlesex Metropolitan Planning Organization.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 01/06/2016 )

    Contracts (3) Progress
    # 115753 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64314 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77850 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Northern Middlesex Metropolitan Planning Organization
    Location: Municipality
    Cities: LOWELL
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Total cost: $5,600,010; YOE: $6,496,012; Funding: STPG; TEC: 7.47 out of 18;
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $5,196,809.60
    State Cost: $1,299,202.40
    Total Cost: $6,496,012.00

    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/29/2005
    Project Status Initiated 11/28/2005
    Project Management