Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STERLING- INTERSECTION IMPROVEMENTS AT ROUTE 12 AND CHOCKSETT ROAD
The purpose of this project is to provide safety improvements to the intersection of Route 12 at Chocksett Road. The work shall consist of the reconfiguration of the intersection, full depth reconstruction, and the addition of pedestrian and bicycle accomodations.
Location:
  • Town of Sterling
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Byron Beauregard
    Construction Bid Price: $4,332,104.50
    District: District 3

    Contracts (1) Progress
    # 97591 -- Construction Contract
    Roadway Reconstruction and Related Work (Including 2 Roundabouts) along a Section of Route 12 (Leominster Road) at Chocksett Road and the I-190 Ramps. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/03/2017
    Contract Information
    Project Designer:
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/29/2005
    Project Status Initiated 11/29/2005
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 08/15/2016
    100% Design 100% Package Comments to DE 09/15/2016
    25% Design 25% Package Received 04/07/2015
    25% Design 25% Package Comments to DE 08/07/2015
    25% Design Design Public Hearing 02/23/2016
    75% Design 75% Package Received 04/22/2016
    75% Design 75% Package Comments to DE 07/14/2016
    Final Design PS&E Received 08/15/2016
    Final Design PS&E to FAPRO 08/22/2016