CHARLEMONT- BRIDGE DECK REPLACEMENT, C-05-012, STATE ROUTE 2 OVER THE DEERFIELD RIVER
Location:
  • Town of Charlemont
  • Resident Engineer: Charles Najimy
    Construction Contract Value: $4,739,693.00
    Construction Bid Price: $4,272,630.00
    Initial Construction Estimate: $3,519,386.50
    District: District 1

    Contracts (1) Progress
    # 51847 -- Construction Contract
    Bridge Deck Replacment(C-05-012) Route 2 (Mohawk Trail) over the Deerfield River Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/19/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/01/2005
    Project Review Committee Letter 12/27/2005
    Project Status Initiated 11/30/2005
    Project Status Advertised 08/05/2006
    Project Management
    75% Design 75% Package Received 04/03/2006
    Final Design PS&E Received 07/20/2006
    Final Design PS&E to FAPRO 07/20/2006