Project Description:
FALL RIVER- BRIDGE BETTERMENT, F-02-041, HIGHLAND AVENUE OVER ROUTE 24 (SB)
The work for the Highland Avenue Northbound over Route 24 Southbound project shall consist of removing and replacing the reinforced concrete deck, cleaning and painting the structural steel, removing and replacing the existing joints, removing and replacing deteriorated stiffeners, cleaning and patching deterioration on the concrete surfaces of the abutments and walls, cleaning the graffiti off the bridge, removing the existing safety walk and safety curb, placing concrete barriers over the existing through girders for use as new bridge rail, and placing highway guardrail transitions.
Location:
  • City of Fall River
  • Resident Engineer: David Ribeiro
    Construction Contract Value: $1,847,365.00
    Construction Bid Price: $1,741,965.00
    Initial Construction Estimate: $2,090,694.00
    District: District 5

    Contracts (1) Progress
    # 56387 -- Construction Contract
    Bridge Rehabilitation (F-02-041) (Steel) Highland Avenue over Route 24 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/27/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Status Initiated 12/07/2005
    Project Status Advertised 07/05/2008
    Project Management
    75% Design 75% Package Received 03/03/2006
    Final Design PS&E Received 09/15/2006
    Final Design PS&E to FAPRO 09/20/2006
    Consultant Contract Process Scope to DE 12/04/2006
    Consultant Contract Process NTP Issued 01/04/2007
    Consultant Contract Process Workhours Approved 12/21/2006