Project Description:
WALTHAM- INTERSTATE MAINTENANCE & RELATED WORK ON I-95.
The I-95 resurfacing project begins at the Weston/Waltham town line (MM 40.65). The project then continues north in the town of Waltham ending at the Waltham/Lexington town line (MM 44.78). The length of project is 21,810-feet or 4.131 miles. The highway mainline with be resurfaced as well as the ramps within the limits of work. The work shall consist of: Full width 1.5 inch asphalt pavement micromilling and overlaying with hot mixed asphalt (HMA); 2.25 inch superpave intermediate and 1.5 inch asphalt rubber gap graded friction course. All mainline HMA courses (base, intermediate, friction) on this project shall be warm mix technology; Removing and discarding guardrail; Upgrading guardrail and end treatments; Excavating the existing median and replacing with a paved high speed shoulder with concrete tall wall safety shape barrier; Removing and discarding the existing median granite edging; Installing bridge rail to highway guardrail transitions; Adjusting and rebuilding drainage structures within the roadway surface; Installing hook lock frames and grates on existing and proposed catch basins; Installing drainage structures in the newly constructed high speed shoulder; Constructing storm water improvements including wet ponds and gravel detention basins; Handling, stabilizing, disposal and re-using of contaminated soils from the highway median; Installing anti-fatigue rumble strips on the high speed and low speed shoulders; Installing pavement markings and slotted pavement markers; Traffic management including temporary concrete barriers; Installing traffic data collection stations Installing replacing scored concrete with milled rumble strips; Placing pavement milling mulch for shoulders and incidental items of work as required by the Engineer.
Location:
  • City of Waltham
  • Resident Engineer: Gennady Shkolnikov
    Construction Contract Value: $25,785,548.00
    Construction Bid Price: $22,425,199.05
    Initial Construction Estimate: $22,296,620.00
    District: District 4

    Contracts (2) Progress
    # 57598 -- Design -- Hwy Eng Open End
    Work will consist of providing design and engineering services to MassHighway on a task order basis for various statewide Value Engineering Studies. Final
    # 67601 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 95. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/08/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/22/2006
    Project Status Initiated 12/22/2005
    Project Status Advertised 08/28/2010
    Project Management
    100% Design 100% Package Received 07/27/2010
    100% Design 100% Plans Approved 08/26/2010
    25% Design Design Public Hearing 03/04/2010
    75% Design 75% Package Received 11/05/2009
    Final Design PS&E Received 08/26/2010
    Final Design PS&E to FAPRO 08/27/2010