Project Description:
|
WALTHAM- INTERSTATE MAINTENANCE & RELATED WORK ON I-95.
The I-95 resurfacing project begins at the Weston/Waltham town line (MM 40.65). The project then continues north in the town of Waltham ending at the Waltham/Lexington town line (MM 44.78). The length of project is 21,810-feet or 4.131 miles. The highway mainline with be resurfaced as well as the ramps within the limits of work.
The work shall consist of:
Full width 1.5 inch asphalt pavement micromilling and overlaying with hot mixed asphalt (HMA); 2.25 inch superpave intermediate and 1.5 inch asphalt rubber gap graded friction course. All mainline HMA courses (base, intermediate, friction) on this project shall be warm mix technology;
Removing and discarding guardrail;
Upgrading guardrail and end treatments;
Excavating the existing median and replacing with a paved high speed shoulder with concrete tall wall safety shape barrier;
Removing and discarding the existing median granite edging;
Installing bridge rail to highway guardrail transitions;
Adjusting and rebuilding drainage structures within the roadway surface;
Installing hook lock frames and grates on existing and proposed catch basins;
Installing drainage structures in the newly constructed high speed shoulder;
Constructing storm water improvements including wet ponds and gravel detention basins;
Handling, stabilizing, disposal and re-using of contaminated soils from the highway median;
Installing anti-fatigue rumble strips on the high speed and low speed shoulders;
Installing pavement markings and slotted pavement markers;
Traffic management including temporary concrete barriers;
Installing traffic data collection stations
Installing replacing scored concrete with milled rumble strips;
Placing pavement milling mulch for shoulders and incidental items of work as required by the Engineer.
|