Project Description:
CHESTERFIELD- RECONSTRUCTION OF EAST STREET, INCLUDES CULVERT REPLACEMENT OF C-12-026 (BAKER BROOK)
This project begins at the Westhampton Town Line and proceeds north-westerly for 3.08 miles to the intersection of South Street. The roadway currently exhibits potholes, alligator and block cracking, delaminating, raveling and rutting. Proposed improvements would include reclaiming the existing roadway, resurfacing with hot mix asphalt, drainage improvements, guardrail installation, and intersection improvements at Stage Road to improve visibility for turning vehicles. Drainage improvements include the installation of cross-drains and sub-drain and replacing a deteriorating steel culvert, four feet in diameter, with a concrete box culvert wide enough to allow the installation of guard rail. The Baker Brook culvert crossing is approximately 1100 feet west of the Stage Road intersection. New pavement markings and traffic signs, including “Share the Road” signs are proposed to improve safety for drivers, bicyclists and pedestrians who use this road.
Location:
  • Town of Chesterfield
  • Resident Engineer: Michael Wall
    Construction Contract Value: $2,251,910.00
    Construction Bid Price: $1,986,518.50
    Initial Construction Estimate: $2,774,941.00
    District: District 1

    Contracts (1) Progress
    # 62155 -- Construction Contract
    Roadway Reconstruction and Related Work on East Street. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/11/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/21/2006
    Project Status Initiated 01/13/2006
    Project Status Advertised 12/26/2009
    Project Management
    100% Design 100% Package Received 02/10/2009
    100% Design 100% Package Received 07/31/2009
    100% Design 100% Package Comments to DE 10/21/2009
    25% Design 25% Package Received 10/11/2007
    25% Design 25% Package Comments to DE 04/02/2008
    25% Design Design Public Hearing 05/06/2008
    75% Design 75% Package Received 07/28/2008
    Final Design PS&E Received 11/06/2009
    Final Design PS&E to FAPRO 12/21/2009