Project Description:
CHESTER- BRIDGE REPLACEMENT, C-11-020, GEORGE MILLER ROAD OVER THE MIDDLE BRANCH OF THE WESTFIELD RIVER
The proposed project will relocate the new structure on new abutments upstream of the existing bridge by approximately 25 feet. The new structure will consist of precast concrete box beams with an asphalt riding surface and new bridge rail. The proposed span length is 85 feet and the width is 16 feet. The roadway approaches will be modified as necessary and safety upgrades will be made with guardrail, bridge rail transitions, the approach rail and terminal ends.
Location:
  • Town of Chester
  • Resident Engineer: Timothy Moore
    Construction Contract Value: $834,497.00
    Construction Bid Price: $754,089.00
    Initial Construction Estimate: $1,202,287.50
    District: District 1

    Contracts (5) Progress
    # 32176 -- Design -- Footprint Bridge contracts
    Statewide - Footprint Bridge Round 3 - Contract I Final
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79737 -- Construction Contract
    Bridge Replacement (C-11-020) (Steel) - George Miller Road over the Middle Branch of the Westfield River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/21/2006
    Project Status Initiated 01/19/2006
    Project Status Advertised 09/14/2013
    Project Management
    25% Design 25% Package Received 03/03/2008
    25% Design 25% Package Comments to DE 03/19/2013
    25% Design Design Public Hearing 02/11/2013
    75% Design 75% Package Received 05/02/2013
    75% Design 75% Package Comments to DE 06/06/2013
    Final Design PS&E Received 07/25/2013
    Final Design PS&E to FAPRO 09/05/2013
    Consultant Contract Process Scope to DE 03/15/2006
    Consultant Contract Process NTP Issued 06/09/2006