HANOVER- NORTON- PLYMOUTH- SEPTIC UPGRADES AT ROUTE 53, ROUTE 123, OBERY STREET FACILITIES
Location:
  • Town of Hanover
  • Town of Norton
  • Town of Plymouth
  • Resident Engineer: Jeffrey Peterson
    Construction Contract Value: $588,752.00
    Construction Bid Price: $588,752.00
    Initial Construction Estimate: $619,120.00
    District: District 5

    Contracts (1) Progress
    # 52018 -- Construction Contract
    Wash Bay Building with Drain and Septic Upgrades at Route 53, Route123 and Obery Street Facilities. DCAM: GEN'L. BUILD. CONSTR. - (This Project has no Filed Sub-Bids) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/21/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 09/22/2006
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/24/2006
    Project Status Initiated 02/01/2006
    Project Status Advertised 09/30/2006
    Project Management
    Final Design PS&E Received 08/24/2006
    Final Design PS&E to FAPRO 08/31/2006