Project Description:
HUDSON- BRIDGE REPLACEMENT, H-25-003, STATE ROUTE 85 (WASHINGTON STREET) OVER THE ASSABET RIVER
The project consists of replacing or rehabilitating the existing bridge carrying State Route 85 (Washington Street) over the Assabet River in the Town of Hudson. This segment of Route 85 is classified as an Urban Minor Arterial. The existing three span granite/earth filled spandrel arch bridge with a curb-to-curb width of 32 feet and a 6.7 foot sidewalk on each side is proposed to be upgraded to current highway standards. The rehabilitated or new structure and the approach roadways will be constructed within the existing footprint and right of way to the maximum extent possible in order to reduce impact. The most viable bridge option will be determined through the preliminary design process.
Location:
  • Town of Hudson
  • Construction Begins: Summer 2016
    Resident Engineer: Steven Miller
    Construction Bid Price: $4,490,056.00
    District: District 3

    Contracts (3) Progress
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 94803 -- Construction Contract
    Bridge Replacement Br. No. H-25-003 (NEXT Beams) Route 85 (Washington Street) over the Assabet River (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/07/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/22/2006
    Project Status Initiated 02/24/2006
    Project Status Advertised 06/11/2016
    Project Management
    100% Design 100% Package Received 08/28/2015
    100% Design 100% Package Received 12/30/2015
    100% Design 100% Package Comments to DE 11/18/2015
    100% Design 100% Plans Approved 03/01/2016
    100% Design 100% Plans Complete 03/01/2016
    25% Design 25% Package Received 01/24/2011
    25% Design 25% Package Received 10/24/2013
    25% Design 25% Package Received 10/09/2014
    25% Design 25% Package Comments to DE 07/25/2011
    25% Design 25% Package Comments to DE 07/25/2011
    25% Design 25% Package Comments to DE 12/12/2013
    25% Design 25% Package Comments to DE 04/02/2014
    25% Design 25% Package Comments to DE 10/22/2014
    25% Design 25% Package Approved 01/21/2015
    25% Design Design Public Hearing 01/20/2015
    25% Design 25% Plans Complete 01/21/2015
    75% Design 75% Package Received 04/24/2015
    Final Design PS&E Received 03/18/2016
    Final Design PS&E to Peer Reviewer 04/05/2016
    Final Design Peer Review Comments to DE 05/03/2016
    Final Design PS&E to FAPRO 05/16/2016
    Consultant Contract Process Scope to DE 03/11/2010
    Consultant Contract Process NTP Issued 04/08/2010