Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FITCHBURG- INTERSECTION IMPROVEMENTS @ JOHN FITCH HIGHWAY & ASHBY STATE ROAD (ROUTE 31)
The work under this project consists of the construction of a roundabout at the intersection of Ashby State Road and John Fitch Highway. Work also includes full depth road construction, cement concrete sidewalks, modifications of storm drainage system, pavement markings and signage.
Location:
  • City of Fitchburg
  • Resident Engineer: Steven Miller
    Construction Contract Value: $1,224,365.00
    Construction Bid Price: $1,074,350.75
    Initial Construction Estimate: $1,382,079.75
    District: District 3

    Contracts (2) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 61462 -- Construction Contract
    Intersection Inprovements and Related Work at John Fitch Highway and Ashby State Road (Route 31). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/23/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/22/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 08/03/2009
    100% Design 100% Package Comments to DE 08/14/2009
    25% Design 25% Package Received 08/02/2006
    25% Design 25% Package Comments to DE 02/06/2007
    25% Design Design Public Hearing 09/27/2007
    75% Design 75% Package Received 07/31/2008
    75% Design 75% Package Comments to DE 01/22/2009
    Final Design PS&E Received 09/02/2009
    Final Design PS&E to FAPRO 09/15/2009