SOUTHAMPTON- RECONSTRUCTION OF GLENDALE ROAD (PHASE II) FROM COLLEGE HIGHWAY (RT 10) NORTHWESTERLY TO POMEROY MEADOW RD (3,801 FEET)
The project involves roadway reconstruction on town-owned Glendale Road in the Town of Southampton, and includes full depth reconstruction, drainage improvements, improvements to the horizontal and vertical alignment of the roadway, guardrail upgrades, and other incidental work. The length of the project is approximately 3,800 feet, beginning at the intersection of Route 10 and extending to Pomeroy Meadow Road.
Location:
  • Town of Southampton
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Michael Los
    Construction Bid Price: $2,122,667.30
    District: District 2

    Contracts (1) Progress
    # 104960 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Glendale Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/09/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/21/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 07/14/2018
    Project Management
    100% Design 100% Package Received 10/13/2017
    100% Design 100% Package Comments to DE 11/21/2017
    25% Design 25% Package Received 05/08/2008
    25% Design 25% Package Comments to DE 05/15/2009
    25% Design Design Public Hearing 07/28/2009
    75% Design 75% Package Received 11/09/2012
    75% Design 75% Package Comments to DE 05/14/2014
    Final Design PS&E Received 04/03/2018
    Final Design PS&E to Peer Reviewer 04/18/2018
    Final Design Peer Review Comments to DE 05/02/2018
    Final Design PS&E Received - Resub 1 06/20/2018