| Project Description: |
BROCKTON- SIGNAL & INTERSECTION IMPROVEMENTS AT MAIN STREET (ROUTE 28) & PLAIN STREET/KEITH AVENUE
Work consists of traffic signal installation and minor geometric improvements at the Main Street (Route 28) and Plain Street-Keith Avenue intersection.
|
| Location: |
|
| Resident Engineer: | Christopher Sera![]() |
| Construction Contract Value: | $1,164,579.00 |
| Construction Bid Price: | $976,890.50 |
| Initial Construction Estimate: | $1,211,950.50 |
| District: | District 5 |
|
Bridges |
||||||||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||