Project Description:
BROCKTON- SIGNAL & INTERSECTION IMPROVEMENTS AT MAIN STREET (ROUTE 28) & PLAIN STREET/KEITH AVENUE
Work consists of traffic signal installation and minor geometric improvements at the Main Street (Route 28) and Plain Street-Keith Avenue intersection.
Location:
  • City of Brockton
  • Resident Engineer: Christopher Sera
    Construction Contract Value: $1,164,579.00
    Construction Bid Price: $976,890.50
    Initial Construction Estimate: $1,211,950.50
    District: District 5

    Contracts (2) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 68091 -- Construction Contract
    Intersection Improvements and Related Work (IncludingTraffic Signals) – Main Street (Route 28) at Plain Street and Keith Avenue. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/24/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 12/18/2010
    Project Management
    100% Design 100% Package Received 05/04/2010
    100% Design 100% Package Comments to DE 07/14/2010
    25% Design 25% Package Received 01/08/2007
    25% Design 25% Package Comments to DE 06/14/2007
    25% Design Design Public Hearing 03/07/2007
    75% Design 75% Package Received 05/01/2009
    75% Design 75% Package Comments to DE 09/03/2009
    Final Design PS&E Received 10/20/2010
    Final Design PS&E to FAPRO 12/13/2010
    Consultant Contract Process Scope to DE 06/20/2005
    Consultant Contract Process NTP Issued 09/21/2005