COHASSET- HINGHAM- HULL- CULVERT REPLACEMENT, C-17-004, ROUTE 228 OVER STRAITS CHANNEL
This project includes the replacement of the existing West Corner Culvert and sluice gates, located at the Hull/Hingham/Cohasset Town Lines. The project will provide ecological benefits to Straits Pond and reduce flooding potential. The project also includes: roadway reconstruction, retaining walls, installation of sidewalks, granite curbing and driveways, drainage system upgrades, waterline replacement, sanitary sewer line replacement, installation of guardrail, traffic signs, and pavement markings. The approach roadway to the bridge will meet the existing grading. The horizontal alignment will remain essentially the same. The total length of the roadway reconstruction is approximately 870 feet. The bridge will be closed during construction for the certain construction activity and a temporary detour will be established. A single lane of traffic will be used on the bridge for the utility relocations.
Location:
  • Town of Cohasset
  • Town of Hingham
  • Town of Hull
  • Resident Engineer: Kevin Morrissey
    Construction Contract Value: $2,902,406.42
    Construction Bid Price: $2,493,077.00
    Initial Construction Estimate: $2,690,000.00
    District: District 5

    Contracts (1) Progress
    # 57182 -- Construction Contract
    Cohasset-Hingham-Hull- Bridge Replacement (C-17-004=H-26-005) Rte 228 (Hull Street) at West Corner over Straits Channel Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/17/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 08/30/2008
    Project Management
    100% Design 100% Package Received 11/29/2007
    100% Design 100% Package Comments to DE 03/19/2008
    25% Design 25% Package Received 03/03/2006
    25% Design 25% Package Comments to DE 05/30/2006
    25% Design Design Public Hearing 04/19/2007
    75% Design 75% Package Received 12/29/2006
    75% Design 75% Package Comments to DE 05/11/2007
    Final Design PS&E Received 07/25/2008
    Final Design PS&E Received 08/26/2008
    Final Design PS&E to FAPRO 08/27/2008