Project Description:
SANDWICH- INTERSECTION & SIGNAL IMPROVEMENTS AT 2 LOCATIONS AT ROUTE 130 RAMPS & ROUTE 6
The proposed work includes the design of new traffic signals at the end of the two ramps for the Route 6/Route 130 interchange in the Town of Sandwich. The work will also include roadway resurfacing and box widening to provide for exclusive left turn lanes for vehicles entering Route 6 from Route 130.
Location:
  • Town of Sandwich
  • Resident Engineer: Daniel Mastrangelo
    Construction Contract Value: $2,033,842.73
    Construction Bid Price: $1,520,473.38
    Initial Construction Estimate: $1,807,529.50
    District: District 5

    Contracts (2) Progress
    # 48664 -- Design -- Traffic Signing/Signals
    Work will generally consist of preparing Plans, Specs and Estimate for intersection improv. and traffic signal installations associated with the Hwy Safety Improv. Prg (HSIP). Final
    # 67816 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) Route 130 at the Route 6 EB and WB Ramps Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/31/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/28/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 07/06/2010
    100% Design 100% Package Comments to DE 08/16/2010
    25% Design 25% Package Received 07/07/2009
    25% Design 25% Package Comments to DE 10/06/2009
    25% Design Design Public Hearing 11/16/2009
    75% Design 75% Package Received 02/03/2010
    75% Design 75% Package Comments to DE 03/31/2010
    Final Design PS&E Received 09/07/2010
    Final Design PS&E to FAPRO 09/08/2010
    Consultant Contract Process Scope to DE 04/28/2008
    Consultant Contract Process NTP Issued 09/05/2008