Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DANVERS- BRIDGE BETTERMENT, D-03-016 ROUTE 1 (NEWBURY STREET) (NB & SB) OVER ROUTE 62 (MAPLE STREET) (SB)
Location:
  • Town of Danvers
  • Resident Engineer: Susan Cranney
    Construction Contract Value: $4,375,083.00
    Construction Bid Price: $4,129,183.00
    Initial Construction Estimate: $4,211,120.50
    District: District 4

    Contracts (2) Progress
    # 53521 -- Construction Contract
    Bridge Superstructure Replacement (D-03-016) (Steel) Route 1 (Newbury Street) over route 62 (Maple Street) Completed
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/14/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/06/2006
    Project Review Committee Letter 03/24/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 10/14/2006
    Project Management
    Final Design PS&E Received 09/04/2006
    Final Design PS&E to FAPRO 09/13/2006