LAWRENCE- BRIDGE BETTERMENT, L-04-001, ROUTE 28 (BROADWAY) OVER THE MERRIMACK RIVER
The proposed work for the betterment of Route 28 over the Merrimack River project consists of reconstructing the bridge and approach wearing surface; removal and replacement of the reinforced concrete deck slab; and upgrading the bridge and approach guard rails. The existing steel shall be cleaned and painted, and lighting standards replaced. The sidewalk supports and catwalks will also be replaced as needed. Concrete deterioration in the bridge piers, abutments and walls will also be repaired. The work will be performed in three stages with one lane of traffic opened in each direction and one sidewalk to be open at all times for pedestrians.
Location:
  • City of Lawrence
  • Resident Engineer: Robert Bosy
    Construction Contract Value: $10,313,802.00
    Construction Bid Price: $8,488,524.00
    Initial Construction Estimate: $10,960,049.00
    District: District 4

    Contracts (2) Progress
    # 36807 -- Design -- Footprint Bridge contracts
    (Footprint 5 Preservation) Perform design of deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Reconstruction Preservation Program. Final
    # 57342 -- Construction Contract
    Bridge Reconstruction (L-04-001) (Steel) - Route 28 (Broadway) over the Merrimack River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/17/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 03/09/2006
    Project Review Committee Letter 03/24/2006
    Project Status Initiated 03/03/2006
    Project Status Advertised 09/27/2008
    Project Management
    100% Design 100% Package Received 05/20/2008
    100% Design 100% Package Comments to DE 06/30/2008
    100% Design 100% Plans Complete 06/26/2008
    Final Design PS&E Received 09/10/2008
    Final Design PS&E to FAPRO 09/17/2008
    Consultant Contract Process Scope to DE 02/15/2006
    Consultant Contract Process NTP Issued 03/14/2006