BOSTON- BRAINTREE- MILTON- QUINCY- RANDOLPH- TRAFFIC SIGN REPLACEMENT ON I-93
This project will replace and update all overhead and ground mounted guide sign panels, exit gore, warning, regulatory, and route marker panels on the I-93 mainline and intersecting secondary roadways from the Route 24 interchange (Exit 4) in Randolph northerly to the I-90 interchange (Exit 20) in Boston. The project will also replace certain existing portable variable message sign (VMS) panels along I-93 with new overhead and/or ground mounted VMS panels.
Location:
  • City of Boston
  • Town of Braintree
  • Town of Milton
  • City of Quincy
  • Town of Randolph
  • Resident Engineer: Eric Mistretta
    Construction Contract Value: $10,789,840.88
    Construction Bid Price: $4,719,996.24
    Initial Construction Estimate: $5,597,428.00
    District: District 6

    Contracts (1) Progress
    # 69357 -- Construction Contract
    Furnish and Install Overhead and Ground Mounted Guide Signs on Interstate 93. (RE-ADVERTISED) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/27/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/09/2006
    Project Status Initiated 04/06/2006
    Project Status Advertised 09/20/2008
    Project Status Advertised 06/11/2011
    Project Management
    100% Design 100% Package Received 02/08/2008
    100% Design 100% Package Comments to DE 03/21/2008
    100% Design 100% Plans Approved 03/18/2008
    25% Design 25% Package Received 11/13/2006
    25% Design 25% Package Comments to DE 01/11/2007
    25% Design 25% Package Approved 12/11/2006
    75% Design 75% Package Received 07/16/2007
    75% Design 75% Package Comments to DE 11/29/2007
    Final Design PS&E Received 05/02/2011
    Final Design PS&E to FAPRO 05/09/2011
    Consultant Contract Process NTP Issued 06/09/2006