UXBRIDGE- BRIDGE REPLACEMENT, U-02-030, RIVER ROAD OVER THE IRONSTONE BROOK
The proposed project involves replacing the existing 2 span bridge on River Road over the Ironstone Brook and the reconstruction of approximately 600 feet of approach work. The proposed single span steel structure will accommodate two 12 foot wide travel lanes, two 4 foot shoulders, and a safety curb mounted with a steel bridge railing. A sidewalk will not be provided on the bridge as there are no sidewalks on River Road in the vicinity of the bridge. The roadway centerline will be shifted to the north while the south edge of the roadway is maintained. The bridge is proposed to be closed during construction with the use of a signed detour.
Location:
  • Town of Uxbridge
  • Resident Engineer: Scott Fitzgerald
    Construction Contract Value: $2,152,949.65
    Construction Bid Price: $1,663,739.60
    Initial Construction Estimate: $2,076,711.00
    District: District 3

    Contracts (3) Progress
    # 43179 -- Design -- Hwy Eng Open End
    Layout Section requires a consultant to provide the service of Layout plan and written description preparation. Final
    # 58994 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Program. Final
    # 66466 -- Construction Contract
    Bridge Replacement (U--02-030) (Steel) - River Road over Inronstone Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 12/31/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Status Initiated 04/20/2006
    Project Status Advertised 07/24/2010
    Project Management
    25% Design 25% Package Received 12/21/2009
    25% Design 25% Package Comments to DE 02/18/2010
    25% Design Design Public Hearing 03/02/2010
    75% Design 75% Package Received 04/30/2010
    75% Design 75% Package Comments to DE 06/10/2010
    Final Design PS&E Received 06/21/2010
    Final Design PS&E Received 07/15/2010
    Final Design PS&E to FAPRO 07/21/2010
    Consultant Contract Process Scope to DE 08/14/2008
    Consultant Contract Process NTP Issued 03/11/2009
    Consultant Contract Process Workhours Approved 02/20/2009