DEDHAM- BRIDGE REPLACEMENT, D-05-033, PROVIDENCE HIGHWAY OVER MOTHER BROOK; FAP NO. NHP-002S(749)X
This bridge project involves the complete replacement of the Providence Highway Bridge over Mother Brook (Bridge No. D-05-033) in Dedham, MA. The existing 4-span steel beam structure, built in 1934, will be replaced with a single span bridge. The proposed cross section will consist of two 12-foot travel lanes, a 12-foot paved shoulder, and a 6.5-foot sidewalk in both directions. An 18-foot wide raised median will separate each travel direction. Traffic will be maintained during construction, as the bridge will be replaced in stages.
Location:
  • Town of Dedham
  • Resident Engineer: Edward Moschella Jr
    Construction Contract Value: $5,693,339.22
    Construction Bid Price: $4,824,954.75
    Initial Construction Estimate: $5,780,000.00
    District: District 6

    Contracts (8) Progress
    # 37067 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State an/or municipally owned bridges as part of the Bridge Rehabilitation/Replacement/Preservation Program. Final
    # 55859 -- Design -- Hwy Eng Open End
    Work will consist of providing services on an open end basis for various projects which require Chapter 253 Dam Safety Permit Review and Completion. Final
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68939 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 84478 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassDOT and our design consultants on an open end basis for various statewide highway and bridge p Final
    # 85005 -- Construction Contract
    Bridge Replacement Br. No.D-05-033 (Steel) Providence Highway over Mother Brook Completed

    Bridges

    Contract Dates
    Notice to Proceed: 05/01/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 05/10/2006
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 08/13/2014
    100% Design 100% Package Comments to DE 09/05/2014
    25% Design 25% Package Received 12/14/2010
    25% Design 25% Package Received 04/26/2013
    25% Design 25% Package Comments to DE 01/24/2011
    25% Design 25% Package Comments to DE 01/24/2011
    25% Design 25% Package Comments to DE 04/28/2011
    25% Design 25% Package Comments to DE 02/18/2014
    25% Design Design Public Hearing 10/12/2011
    75% Design 75% Package Received 04/30/2014
    75% Design 75% Package Comments to DE 06/25/2014
    Final Design PS&E Received 09/15/2014
    Final Design PS&E to FAPRO 09/16/2014
    Consultant Contract Process Scope to DE 06/08/2006
    Consultant Contract Process NTP Issued 08/28/2008
    Consultant Contract Process Workhours Approved 07/28/2008