Project Description:
MIDDLEBORO- SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 44 @ 4 LOCATIONS: AT CENTER ST, AT EVERETT ST, AT PLYMOUTH ST, AT PLYMPTON ST
The project involves upgrading four traffic signals. The work consists of furnishing & installing traffic signals at the intersection of Route 44 and (1) Old Center Street, (2) Everett Street, (3) Plymouth Street and (4) Plymton Street (Route 105). The work also consists of roadway widening, geometric improvements, retaining wall construction and landscaping.
Location:
  • Town of Middleborough
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $3,229,822.77
    Construction Bid Price: $2,747,225.16
    Initial Construction Estimate: $3,043,583.00
    District: District 5

    Contracts (3) Progress
    # 34562 -- Design -- Hwy Eng Open End
    Provide engineering services to the Projects Division on an open end basis for various highway and bridge projects. Final
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 56811 -- Construction Contract
    Middleborough- Intersection Improvements and Related Work at 4 Locations on Route 44 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/31/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/13/2006
    Project Status Initiated 05/30/2006
    Project Status Advertised 08/09/2008
    Project Management
    100% Design 100% Package Received 06/19/2008
    100% Design 100% Package Comments to DE 07/16/2008
    25% Design Design Public Hearing 05/14/2008
    75% Design 75% Package Received 04/21/2006
    75% Design 75% Package Received 02/12/2008
    75% Design 75% Package Comments to DE 07/17/2006
    Final Design PS&E Received 07/31/2008
    Final Design PS&E to FAPRO 08/05/2008
    Consultant Contract Process NTP Issued 01/17/2006