Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WESTFORD- RECONSTRUCTION OF ROUTE 110 AT BOSTON ROAD AND CARLISLE ROAD (MINOT'S CORNER)
The proposed project will reconstruct a section of Route 110 in the Town of Westford. The project extends from Minot's Corner to Nixon Road for a length of approximately 3,100 feet. The corridor includes the following intersections: Littleton Road at Westford Plaza Main Drive, Littleton Drive at Westford Plaza East Drive, Little Road at Nixon Road, Little Road at Boston Road and Carlisle Road and Littleton Road at McDonald's driveway and Westford Valley Marketplace driveway.
Location:
  • Town of Westford
  • Resident Engineer: Arvind Patel
    Construction Contract Value: $3,863,065.00
    Construction Bid Price: $3,491,987.50
    Initial Construction Estimate: $3,984,402.50
    District: District 3

    Contracts (4) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68385 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 75587 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of Littleton Road (Route 110) at Intersection of Boston and Carlisle Roads. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/14/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Other types not listed
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 05/31/2006
    Project Status Advertised 09/15/2012
    Project Management
    100% Design 100% Package Received 03/01/2012
    100% Design 100% Package Comments to DE 04/17/2012
    25% Design 25% Package Received 03/15/2010
    25% Design 25% Package Comments to DE 06/03/2010
    25% Design Design Public Hearing 09/29/2010
    75% Design 75% Package Received 09/29/2011
    75% Design 75% Package Comments to DE 01/19/2012
    Final Design PS&E Received 05/30/2012
    Final Design PS&E to FAPRO 09/12/2012