Project Description:
MARLBOROUGH- RECONSTRUCTION OF ROUTE 85 (MAPLE STREET)
The proposed project will consist of full depth roadway reconstruction and resurfacing, new sidewalk construction, the re-alignment of Framingham Road, and enhanced bicycle and pedestrian accommodations. Other items will include new traffic signal systems, minor drainage system and utility adjustments, improved roadway signage, enhanced crosswalks, landscaping and pavement delineation/striping for vehicles, bicyclists and pedestrians traveling through the Maple Street corridor. The project limits are between the Southborough Town Line and John Street. The project length is approximately 6,175 linear feet (1.17 miles).
Location:
  • City of Marlborough
  • Construction Begins: Winter 2017/2018
    Resident Engineer: James Kummer
    Construction Bid Price: $4,649,680.00
    District: District 3

    Contracts (2) Progress
    # 100844 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 85 (Maple Street). Completed
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/14/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 05/31/2006
    Project Status Advertised 06/24/2017
    Project Management
    25% Design 25% Package Received 03/13/2015
    25% Design 25% Package Comments to DE 06/24/2015
    25% Design Design Public Hearing 12/01/2015
    75% Design 75% Package Received 11/07/2016
    75% Design 75% Package Comments to DE 12/14/2016
    Final Design PS&E Received 04/17/2017
    Final Design Peer Review Comments to DE 03/15/2017
    Final Design PS&E to FAPRO 06/16/2017
    Final Design PS&E Received - Resub 1 06/15/2017