Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WEST BRIDGEWATER- PARK & RIDE UPGRADE AT ROUTE 106, WEST CENTER STREET & PLEASANT STREET
This project consists of the construction of a 40 space Park and Ride lot, and the overlay and restriping of the existing Park and Ride lot.
Location:
  • Town of West Bridgewater
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $446,309.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project