ERVING- RECONSTRUCTION OF ROUTE 2 (ERVING CENTER) FROM MM 62.9 TO MM 63.9
The project involves intersection/roadway alignment improvements, sidewalks, pavement markings and signage along state-owned Route 2 from the parking area near MM 62.9 to the easterly end of Prospect Street, MM 63.9 in Erving. Potential improvements include lowering the vertical curve on Route 2 between Mountain Road and North Street, geometric and sight distance improvements at various intersections, traffic calming measures, new sidewalks with redesigned crosswalks, and possibly the construction of traffic signals and a dedicated left turn lane in the village center at North Street.
Location:
  • Town of Erving
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Anni H Autio
    Estimated Total Contract Cost: $0.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 06/09/2009 )

    Contracts (1) Progress
    # 49974 -- Design -- Traffic Signing/Signals
    Work will consist of reconstruction and safety improvementsin the Town of Erving - Route 2 at Erving center. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 07/26/2012
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 06/01/2006
    Project Management
    Consultant Contract Process Scope to DE 06/04/2008
    Consultant Contract Process NTP Issued 06/09/2009
    Consultant Contract Process Workhours Approved 01/02/2009