Project Description:
SPRINGFIELD- INTERSECTION & SIGNAL IMPROVEMENTS ON ROOSEVELT AVENUE, PAGE BOULEVARD AND BAY STREET (MEMORIAL INDUSTRIAL PARK II)
The proposed improvements are for three intersections along the Roosevelt Avenue and Page Boulevard (Route 20A) corridors. (1) At the intersection of Roosevelt Avenue and Page Boulevard, three of the four approaches (the exception is Roosevelt Avenue north of the intersection) will be widened to accommodate an additional travel lane. The traffic signals will be updated and will include an exclusive pedestrian phase, bicycle detection and emergency vehicle pre-emption. (2) At the intersection of Page Blvd. and the I-291 westbound off-ramp, new traffic signals will be installed and these signals will be coordinated with the nearby Page Blvd./Roosevelt Ave. traffic signals. These new signals at the I-291 off-ramp will also have emergency vehicle pre-emption and bicycle detection. (3) At the intersection of Roosevelt Avenue and Bay Street, the traffic signals will be updated and will include push-button pedestrian signals, emergency vehicle pre-emption and bicycle detection. The westbound approach of Bay Street will also be widened to three lanes westbound and one lane eastbound, and there will be other minor geometric improvements as well.
Location:
  • City of Springfield
  • Resident Engineer: Donald Tatro, Jr.
    Construction Contract Value: $2,310,853.00
    Construction Bid Price: $1,998,557.50
    Initial Construction Estimate: $2,280,654.50
    District: District 2
    Current Status: Road under construction (as of 05/21/2008)

    Contracts (1) Progress
    # 54022 -- Construction Contract
    Springfield - Intersection Reconstruction and Related Work along Roosevelt Avenue (Rte 20A) and Page Boulevard Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/26/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Road under construction
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 06/01/2006
    Project Status Advertised 09/08/2007
    Project Management
    100% Design 100% Package Received 07/20/2007
    100% Design 100% Package Comments to DE 08/23/2007
    25% Design 25% Package Received 11/15/2006
    25% Design 25% Package Comments to DE 12/29/2006
    25% Design Design Public Hearing 02/07/2007
    75% Design 75% Package Received 04/02/2007
    75% Design 75% Package Comments to DE 07/18/2007
    Final Design PS&E Received 09/04/2007
    Final Design PS&E to FAPRO 09/05/2007