Project Description:
PLAINFIELD- REHABILITATION OF ROUTE 116
This project is a reclamation and resurfacing project beginning at the Intersection of Route 8A and ending at the Savoy town line for a distance of 1.9 miles. Included in this project will be an assessment of the current drainage and guardrail systems with improvements/replacements made as required. Signs will also be removed and replaced as necessary.
Location:
  • Town of Plainfield
  • Resident Engineer: Timothy Moore
    Construction Contract Value: $1,468,716.00
    Construction Bid Price: $1,285,346.50
    Initial Construction Estimate: $1,616,778.00
    District: District 1

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 76187 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 116 (West Main Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/19/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 06/08/2006
    Project Review Committee Letter 06/30/2006
    Project Status Initiated 06/01/2006
    Project Status Advertised 11/03/2012
    Project Management
    25% Design 25% Package Received 12/21/2009
    25% Design 25% Package Received 02/05/2010
    25% Design 25% Package Comments to DE 08/27/2010
    25% Design Design Public Hearing 11/18/2010
    75% Design 75% Package Received 08/24/2011
    75% Design 75% Package Comments to DE 01/16/2012
    Final Design PS&E Received 07/06/2012
    Final Design PS&E Received 08/02/2012
    Final Design PS&E to FAPRO 10/31/2012