DISTRICT 5- TREE TRIMMING & SIGHT DISTANCE IMPROVEMENT
Location:
Resident Engineer: Stephen Soares
Construction Contract Value: $730,556.00
Construction Bid Price: $654,756.00
Initial Construction Estimate: $902,325.00
District: District 5

Contracts (1) Progress
# 54509 -- Construction Contract
District 5- Tree Trimming and Sight Distance Clearing at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/13/2008
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/14/2006
    Project Review Committee Letter 09/18/2006
    Project Status Initiated 07/26/2006
    Project Status Advertised 02/09/2008
    Project Management
    100% Design 100% Package Received 09/18/2007
    Final Design PS&E Received 09/26/2006
    Final Design PS&E to FAPRO 09/19/2007