Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WINCHENDON- BRIDGE REPLACEMENT, W-39-001, HARRIS ROAD OVER TARBELL BROOK
This locally-owned bridge replacement project is located 1.6 miles west of Route 12 by West Street. Curb to curb bridge width will be increased from 14.3 feet to 18 feet. There will be no sidewalk. The bridge will be closed during construction and a detour provided.
Location:
  • Town of Winchendon
  • Resident Engineer: Matthew Minihan
    Construction Bid Price: $2,129,943.00
    District: District 2

    Contracts (3) Progress
    # 54834 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 77891 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90317 -- Construction Contract
    Bridge Replacement Br. No. W-39-001 (Steel) Harris Road over Tarbell Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/10/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Tabled 09/14/2006
    Project Review Committee PRC Approved 12/14/2006
    Project Review Committee Letter 01/03/2007
    Project Status Initiated 08/08/2006
    Project Status Advertised 08/22/2015
    Project Management
    100% Design 100% Package Received 06/18/2015
    100% Design 100% Package Comments to DE 07/20/2015
    100% Design 100% Plans Approved 07/24/2015
    25% Design 25% Package Received 10/08/2014
    25% Design 25% Package Comments to DE 11/07/2014
    25% Design 25% Package Comments to DE 12/05/2014
    25% Design 25% Package Approved 12/19/2014
    25% Design Design Public Hearing 12/18/2014
    75% Design 75% Package Received 03/17/2015
    75% Design 75% Package Comments to DE 04/23/2015
    75% Design 75% Plans Approved 05/26/2015
    Final Design PS&E Received 08/05/2015
    Final Design PS&E Received 09/11/2015
    Final Design PS&E to FAPRO 08/19/2015
    Final Design PS&E to FAPRO 09/16/2015
    Consultant Contract Process NTP Issued 09/12/2013