LITTLETON- BRIDGE REPLACEMENT, L-13-021, TAYLOR STREET OVER I-495 (NB & SB), L-13-022, I-495 (NB & SB) OVER ROUTE 2 & L-13-023, I-495 (NB & SB) OVER RAILROAD BRIDGE
This bridge project will result in the removal of the existing bridges of I-495 over Route 2 and the construction of new bridges on new alignments to allow for construction staging. The project also will result in the removal of the Taylor Street Bridge over I-495 and the construction of a new bridge in the same horizontal alignment. The bridge carrying I-495 over the MBTA Commuter Rail Line will also be rehabilitated. Work includes approximately 2,800 feet of highway approach work, modifications to the interchange ramps to meet the new alignment, modification to the Taylor Street roadway profile, upgrading the storm water drainage system, highway guards, loam and seeding, and other necessary incidental work. The bridge will be constructed in stages to accommodate existing traffic throughout construction.
Location:
  • Town of Littleton
  • Resident Engineer: Linda Terry
    Construction Contract Value: $40,143,379.03
    Construction Bid Price: $26,760,631.00
    Initial Construction Estimate: $37,619,310.33
    District: District 3

    Contracts (11) Progress
    # 36808 -- Design -- Footprint Bridge contracts
    (Footprint 5 Preservation) Perform design of deficient State and/or municipally owned bridges as part of the Bridge Rehabilitation/Reconstruction Preservation Program. Final
    # 54826 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54835 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57465 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57598 -- Design -- Hwy Eng Open End
    Work will consist of providing design and engineering services to MassHighway on a task order basis for various statewide Value Engineering Studies. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 68382 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 75501 -- Construction Contract
    Bridge Replacement Br. No. L-13-021 (Concrete) Taylor Street over Interstate 495 (NB & SB), Br. No. L-13-022 (Concrete) Interstate 495 (NB & SB) over Route 2 and Br. No. L-13- Completed
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/25/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/14/2006
    Project Review Committee Letter 10/03/2006
    Project Status Initiated 08/24/2006
    Project Status Advertised 09/08/2012
    Project Management
    25% Design 25% Package Received 03/11/2010
    25% Design 25% Package Received 03/08/2011
    25% Design 25% Package Received 12/16/2011
    25% Design 25% Package Comments to DE 04/25/2011
    25% Design 25% Package Comments to DE 04/17/2012
    25% Design Design Public Hearing 05/05/2010
    75% Design 75% Package Received 05/30/2012
    75% Design 75% Package Comments to DE 08/21/2012
    Final Design PS&E Received 09/05/2012
    Final Design PS&E to FAPRO 09/05/2012
    Consultant Contract Process Scope to DE 12/20/2007
    Consultant Contract Process NTP Issued 02/24/2009