GREENFIELD- LIGHTING UPGRADE & IMPROVEMENTS @ I-91/ROUTE 2/ROUTE 2A ROTARY
The proposed work involves replacing the existing highway lighting system in the I-91/Rte.2/Rte.2A rotary area. The following new highway lighting components would be installed at the rotary and approach roadways: lighting control cabinet; service connection to a Western Massachusetts Electric facility; light poles and foundations, luminaires, pull boxes, conduits, and wiring. In addition, the work involves the removal, dismantling, transporting, delivery, and stacking of the existing light poles, luminaires, and lighting load center equipment to the MassDOT District 2 facilities.
Location:
  • Town of Greenfield
  • Resident Engineer: Victor LaMountain
    Construction Contract Value: $968,581.00
    Construction Bid Price: $789,619.10
    Initial Construction Estimate: $945,155.30
    District: District 2

    Contracts (2) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 67425 -- Construction Contract
    Highway Lighting Installation at the Exit 26 Ramps on I-91 and the Routes 2/2A Rotary. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/10/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/14/2006
    Project Review Committee Letter 10/03/2006
    Project Status Initiated 08/31/2006
    Project Status Advertised 09/04/2010
    Project Management
    100% Design 100% Package Received 01/29/2010
    25% Design 25% Package Received 06/29/2007
    75% Design 75% Package Received 09/01/2009
    75% Design 75% Package Comments to DE 11/17/2009
    Final Design PS&E Received 06/29/2010
    Final Design PS&E to FAPRO 08/31/2010
    Consultant Contract Process NTP Issued 03/12/2009