WESTBOROUGH- INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 9 & LYMAN STREET
The project limits from 3000 feet west of Lyman Street to 1500 feet east of Lyman St, about 4500 feet long. The project include widening and new signal equipment.
Location:
  • Town of Westborough
  • Construction Begins: Spring 2017
    Resident Engineer: Roger Wykes
    Construction Bid Price: $7,681,882.50
    District: District 3

    Contracts (5) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 97774 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) along a Section of Route 9 (Boston-Worcester Turnpike) at Lyman Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/31/2017
    Contract Information
    Project Designer: Consultant
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/14/2006
    Project Review Committee Letter 10/03/2006
    Project Status Initiated 09/01/2006
    Project Status Advertised 09/10/2016
    Project Management
    100% Design 100% Package Received 03/03/2016
    100% Design 100% Package Comments to DE 05/05/2016
    25% Design 25% Package Received 05/05/2011
    25% Design 25% Package Received 04/24/2014
    25% Design 25% Package Comments to DE 06/10/2014
    25% Design Design Public Hearing 02/05/2015
    75% Design 75% Package Received 08/19/2015
    75% Design 75% Package Comments to DE 10/15/2015
    Final Design PS&E Received 08/03/2016
    Final Design PS&E to Peer Reviewer 03/10/2016
    Final Design Peer Review Comments to DE 04/01/2016
    Final Design PS&E to FAPRO 09/06/2016