Project Description:
WORCESTER- BIKE PATH CONSTRUCTION, FROM TAINTER STREET TO KILBY STREET AND RESURFACING KILBY AND GARDNER STREETS
The proposed improvements involve construction of a pedestrian/bikeway path and retaining wall along the westerly perimeter of the redeveloped site to restore access through this section of Main South. The proposed path will be approximately fourteen feet wide and will be lighted along its length. The City of Worcester will own and maintain the path. This project also includes the resurfacing of Kilby and Gardner Streets.
Location:
  • City of Worcester
  • Resident Engineer: Michael Chauvin
    Construction Contract Value: $2,672,238.84
    Construction Bid Price: $2,483,264.40
    Initial Construction Estimate: $2,600,000.00
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 86124 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Bike Path and Retaining Walls) along Sections of Kilby and Gardner Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/07/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/22/2010
    Project Initiation Form PIF Entered 03/23/2010
    Project Initiation Form PRC Submitted 03/23/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 06/03/2010
    Project Status Advertised 12/20/2014
    Project Management
    25% Design 25% Package Received 04/29/2011
    25% Design 25% Package Received 12/24/2013
    25% Design 25% Package Comments to DE 04/03/2012
    25% Design Design Public Hearing 05/09/2012
    75% Design 75% Package Received 03/24/2014
    75% Design 75% Package Comments to DE 05/05/2014
    Final Design PS&E Received 10/10/2014
    Final Design PS&E Received 12/08/2014
    Final Design PS&E to FAPRO 12/17/2014
    Consultant Contract Process Scope to DE 04/14/2009